CCR Rule Compliance Data and Information

Spurlock Station Landfill

 

Reports

                       

Location Restrictions 257.107(e)

Placement above the uppermost aquifer

Seismic impact zones

Unstable areas

Fault areas

Wetlands

            Spurlock_Landfill_20170329_Location Restrictions_Area C Phase 3

                                Spurlock_Landfill_20170620_Location Restrictions For Existing Landfill

                                Spurlock_Landfill_20170620_Location Restrictions for Existing Landfill Supplemental Certification

Design Criteria

Pre-Construction design and construction certifications for new CCR Landfills and Lateral Expansions 257.107 (f) (1)

Spurlock_Landfill_20160607_Pre-Construction Design and Construction Certifications for Area C Phase

                Spurlock_Landfill_20180712_Pre-Construction Design and Construction Certifications for AreaC Phase4

Post-Construction certifications for new CCR Landfills and Lateral Expansions 257.107 (f) (2)

                Spurlock_Landfill_20180131_Post-Construction Design and Construction Certifications for Area C Phase 3

            Spurlock_Landfill_20181023_Post-Construction Design and Construction Certification_Area C Phase 3-B

Operating Criteria

Fugitive Dust Plan 257.107 (g) (1)

                Spurlock_20151006_Fugitive Dust Control Plan

                Spurlock_20151006_Fugitive Dust Control Plan Supplemental Certification

Annual Fugitive Dust Report 257.107 (g) (2)

                Spurlock_20161201_Annual Fugitive Dust Report

                Spurlock_20171201_Annual Fugitive Dust Report

Initial and Periodic Run-on Run-off Control System Plan (Landfills) 257.107 (g) (3)

                Spurlock_Landfill_20161013_Run-On and Run-Off Control System Plan

                Spurlock_Landfill_20161013_Run-On and Run-Off Control System Plan Supplemental Certification               

Spurlock_Landfill_20180131_Run-On and Run-Off Control System Plan for Area C Phase 3

                Spurlock_Landfill_20181023_Run-On and Run-Off Control System Plan_Area C Phase 3-B

Corrective Measures to respond to a deficiency or release 257.107 (g) (6)

Initial and Periodic Annual Inspection Landfills 257.107 (g) (7)

                Spurlock_Landfill_20160114_Annual CCR Inspection Report        

                Spurlock_Landfill_20170306_Annual CCR Inspection Report

Spurlock_Landfill_20180112_Annual CCR Inspection Report

Groundwater

Annual Groundwater Monitoring and Corrective Action Report 257.107 (h) (1)  

                Spurlock_Landfill_20180131_Annual GWM & CA Report

Groundwater Monitoring System Design and Construction Certification 257.107 (h) (2)  

                Spurlock_Landfill_20171017_Groundwater Monitoring System Certification

Certification of the Selection of Statistical Method (Groundwater Monitoring Plan) 257.107 (h) (3)  

                Spurlock_Landfill_20171010_Statistical Method Selection & Certification

Notification that an assessment monitoring program has been established 257.107 (h) (4)  

Notification that the CCR Unit is returning to a detection monitoring program 257.107 (h) (5)  

Notification that a constituent level is statistically significant 257.107 (h) (6)  

Notification that an assessment of corrective measures has been initiated 257.107 (h) (7)  

Assessment of corrective measures 257.107 (h) (8)  

Semi-annual reports describing remedy selection 257.107 (h) (9)   

Notification of remedy completion 257.107 (h) (10) 

 

Closure/Post Closure

Written Closure Plan 257.107 (i) (4)

                Spurlock_Landfill_20161013_Closure Plan

                Spurlock_Landfill_20161013_Closure Plan Supplemental Certification

Demonstration for time extension to Initiate Closure 257.107 (i) (5)  

Demonstration for time extension to Complete Closure 257.107 (i) (6)  

Notification of Intent to Initiate Closure 257.107(i) (7)

Notification of Closure Completion 257.107 (i) (8)  

Notification of Recording a Notation on the Deed 257.107 (i) (9)  

Notification of Intent to comply with Alternative Closure requirements 257.107 (i) (10)  

Annual progress reports under the alternative closure requirements 257.107 (i) (11)  

Written post closure plan and any amendment of the plan 257.107 (i) (12)  

                Spurlock_Landfill_20161013_Post-Closure Plan

                Spurlock_Landfill_20161013_Post-Closure Plan Supplemental Certification

Notification of Post-Closure Care Completion 257.107 (i) (13)